23-0234

9800 HIBISCUS DR

Finaled

Jan 31, 2022

Jan 17, 2023

Dec 02, 2023

ULTIMATE KONSTRUCTION

Residential ADU Conversion (attached)

type created notes
Not Yet Determined yes ref # 114660

CONVERT (E) GARAGE TO ADU(434SF) 1BED, 1BATH, KITCHEN, LIVING ROOM. Main sfr address 9802 Hibiscus Dr.

Finaled

inspections:

date status requested inspection assigned to inspector phone
May 24, 2023 Approved 940 Building Final Jordan Wiley tel:
May 22, 2023 NOT READY 940 Building Final Jordan Wiley tel:
Apr 19, 2023 Approved 145 Drywall Peter Garcia tel:
Apr 11, 2023 Approved 160 Brown Coat Vicki Bolanis tel:
Apr 11, 2023 Partial Pass 145 Drywall Vicki Bolanis tel:
Apr 04, 2023 Approved 245 Gas Test Jordan Wiley tel:
Apr 04, 2023 Approved 170 Windows Jordan Wiley tel:
Apr 04, 2023 Approved 150 Exterior Lath Jordan Wiley tel:
Apr 04, 2023 Approved 130 Shear Walls / Pre-Wrap Jordan Wiley tel:
Apr 04, 2023 Approved 140 Insulation Jordan Wiley tel:
Apr 04, 2023 Approved 135 Framing Jordan Wiley tel:
Apr 03, 2023 Corrections 130 Shear Walls / Pre-Wrap Todd Hartwig 714-741-5333
Apr 03, 2023 Corrections 140 Insulation Todd Hartwig 714-741-5333
Apr 03, 2023 Corrections 135 Framing Todd Hartwig 714-741-5333
Mar 28, 2023 NOT READY 305 Rough Mechanical Jordan Wiley tel:
Mar 28, 2023 NOT READY 225 Rough Plumbing Jordan Wiley tel:
Mar 28, 2023 NOT READY 420 Rough Wiring Jordan Wiley tel:
Mar 28, 2023 Partial Pass 140 Insulation Jordan Wiley tel:
Mar 22, 2023 Corrections 135 Framing Jordan Wiley tel:
Mar 22, 2023 Corrections 225 Rough Plumbing Jordan Wiley tel:
Mar 22, 2023 Corrections 305 Rough Mechanical Jordan Wiley tel:
Mar 22, 2023 Corrections 420 Rough Wiring Jordan Wiley tel:
Mar 16, 2023 NOT READY 225 Rough Plumbing Vicki Bolanis tel:
Mar 16, 2023 NOT READY 420 Rough Wiring Vicki Bolanis tel:
Mar 16, 2023 NOT READY 305 Rough Mechanical Vicki Bolanis tel:
Mar 16, 2023 NOT READY 135 Framing Vicki Bolanis tel:
Mar 09, 2023 Corrections 135 Framing Vicki Bolanis tel:
Mar 09, 2023 Corrections 305 Rough Mechanical Vicki Bolanis tel:
Mar 09, 2023 Corrections 420 Rough Wiring Vicki Bolanis tel:
Mar 09, 2023 Corrections 225 Rough Plumbing Vicki Bolanis tel:
Feb 03, 2023 Approved 105 Foundation Marco Zamora tel:
Jan 31, 2023 Approved 205 Plumb Soil Groundwork Todd Hartwig 714-741-5333
Jan 31, 2023 Approved 220 Sewer Todd Hartwig 714-741-5333
Jan 30, 2023 Cancel 105 Foundation Todd Hartwig 714-741-5333
none Approved Final Application Evaluation Unassigned  
Feb 28, 2022 Approved Conditional Water Plan Check Unassigned  
Feb 28, 2022 Approved Plan Check (Planning) Chris Chung tel:
Feb 28, 2022 Approved Plan Check (Engineering) Alicia Hofer tel:
Feb 28, 2022 Approved Plan Check (Building) Vinh Vu tel:

Legend

Approved
Inspection passed
Partial Pass
A portion was approved, okay to proceed
Pending
Inspection status not recorded
Not Ready
Insufficient progress to perform inspection
Corrections
Outstanding issues, refer to correction notice
No Access
Job site not available for entry
Cancel
Inspection request called off