21-2423

9766 CENTRAL AVE

Finaled

Feb 08, 2021

Jun 23, 2021

Oct 16, 2022

NONE LISTED

Residential ADU New (detached)

type created notes
Not Yet Determined no missing email

CONSTRUCT (N) 1200sf DETACHED ADU W/ 2-BEDROOMS, 2-BATHROOMS, LIVING ROOM, KITCHEN, DINING, FAMILY ROOM, & LAUNDRY CLOSET. ADD (N) 80sf PORCH. (N) HVAC. MANDATORY MINIMUM 3.0 kWdc PV SOLAR TO BE ON SEPARATE PERMIT. Main sfr address 9762 Central Ave.

Finaled

inspections:

date status requested inspection assigned to inspector phone
Apr 19, 2022 Approved 940 Building Final Sylvia Holloway tel:
Apr 15, 2022 Cancel 940 Building Final Inspector C tel:
Mar 31, 2022 Corrections 940 Building Final Sylvia Holloway tel:
Nov 17, 2021 Approved 160 Brown Coat Mike Austin tel:
Nov 02, 2021 Approved 240 Shower Pan / Test Reuben Cain tel:
Nov 02, 2021 NOT READY 160 Brown Coat Reuben Cain tel:
Oct 20, 2021 Approved 155 Shower Lath / Tile Backer Don Lucas tel:
Oct 20, 2021 Approved 150 Exterior Lath Don Lucas tel:
Oct 20, 2021 Approved 145 Drywall Don Lucas tel:
Oct 04, 2021 Approved 225 Rough Plumbing Reuben Cain tel:
Oct 13, 2021 Approved 140 Insulation Mike Austin tel:
Oct 07, 2021 Approved 230 Underground Gas Piping Reuben Cain tel:
Oct 07, 2021 Approved 135 Framing Reuben Cain tel:
Oct 07, 2021 Approved 216 Water Main / Lateral (Virtual) Reuben Cain tel:
Oct 04, 2021 Approved 420 Rough Wiring Reuben Cain tel:
Oct 01, 2021 Cancel 420 Rough Wiring Inspector C tel:
Sep 28, 2021 Approved 305 Rough Mechanical Reuben Cain tel:
Sep 28, 2021 Approved 130 Shear Walls / Pre-Wrap Reuben Cain tel:
Sep 28, 2021 Approved 170 Windows Reuben Cain tel:
Sep 28, 2021 Approved 125 Roof Sheathing Reuben Cain tel:
Jul 15, 2021 Approved 410 UFER Ground Reuben Cain tel:
Jul 15, 2021 Approved 105 Foundation Reuben Cain tel:
Jul 06, 2021 Approved 220 Sewer Dan Charboneau tel:
Jul 06, 2021 Approved 205 Plumb Soil Groundwork Dan Charboneau tel:
Jul 14, 2021 Cancel 221 Sewer (Virtual) Unassigned  
Jul 14, 2021 Cancel 205 Plumb Soil Groundwork Unassigned  
none Approved Final Application Evaluation Unassigned  
Mar 26, 2021 Approved Conditional Water Plan Check Unassigned  
Mar 29, 2021 Approved Plan Check (Planning) Huong Ly tel:
Mar 26, 2021 Approved Plan Check (Engineering) Alicia Hofer tel:
Mar 26, 2021 Approved Plan Check (Building) Don Lucas tel:
none Approved School District Unassigned  

Legend

Approved
Inspection passed
Partial Pass
A portion was approved, okay to proceed
Pending
Inspection status not recorded
Not Ready
Insufficient progress to perform inspection
Corrections
Outstanding issues, refer to correction notice
No Access
Job site not available for entry
Cancel
Inspection request called off