21-2423
9766 CENTRAL AVE
Finaled
Feb 08, 2021
Jun 23, 2021
Oct 16, 2022
NONE LISTED
Residential ADU New (detached)
type | created | notes |
---|---|---|
Not Yet Determined | no | missing email |
CONSTRUCT (N) 1200sf DETACHED ADU W/ 2-BEDROOMS, 2-BATHROOMS, LIVING ROOM, KITCHEN, DINING, FAMILY ROOM, & LAUNDRY CLOSET. ADD (N) 80sf PORCH. (N) HVAC. MANDATORY MINIMUM 3.0 kWdc PV SOLAR TO BE ON SEPARATE PERMIT. Main sfr address 9762 Central Ave.
Finaled
date | status | requested inspection | assigned to | inspector phone |
---|---|---|---|---|
Apr 19, 2022 | Approved | 940 Building Final | Sylvia Holloway | tel: |
Apr 15, 2022 | Cancel | 940 Building Final | Inspector C | tel: |
Mar 31, 2022 | Corrections | 940 Building Final | Sylvia Holloway | tel: |
Nov 17, 2021 | Approved | 160 Brown Coat | Mike Austin | tel: |
Nov 02, 2021 | Approved | 240 Shower Pan / Test | Reuben Cain | tel: |
Nov 02, 2021 | NOT READY | 160 Brown Coat | Reuben Cain | tel: |
Oct 20, 2021 | Approved | 155 Shower Lath / Tile Backer | Don Lucas | tel: |
Oct 20, 2021 | Approved | 150 Exterior Lath | Don Lucas | tel: |
Oct 20, 2021 | Approved | 145 Drywall | Don Lucas | tel: |
Oct 04, 2021 | Approved | 225 Rough Plumbing | Reuben Cain | tel: |
Oct 13, 2021 | Approved | 140 Insulation | Mike Austin | tel: |
Oct 07, 2021 | Approved | 230 Underground Gas Piping | Reuben Cain | tel: |
Oct 07, 2021 | Approved | 135 Framing | Reuben Cain | tel: |
Oct 07, 2021 | Approved | 216 Water Main / Lateral (Virtual) | Reuben Cain | tel: |
Oct 04, 2021 | Approved | 420 Rough Wiring | Reuben Cain | tel: |
Oct 01, 2021 | Cancel | 420 Rough Wiring | Inspector C | tel: |
Sep 28, 2021 | Approved | 305 Rough Mechanical | Reuben Cain | tel: |
Sep 28, 2021 | Approved | 130 Shear Walls / Pre-Wrap | Reuben Cain | tel: |
Sep 28, 2021 | Approved | 170 Windows | Reuben Cain | tel: |
Sep 28, 2021 | Approved | 125 Roof Sheathing | Reuben Cain | tel: |
Jul 15, 2021 | Approved | 410 UFER Ground | Reuben Cain | tel: |
Jul 15, 2021 | Approved | 105 Foundation | Reuben Cain | tel: |
Jul 06, 2021 | Approved | 220 Sewer | Dan Charboneau | tel: |
Jul 06, 2021 | Approved | 205 Plumb Soil Groundwork | Dan Charboneau | tel: |
Jul 14, 2021 | Cancel | 221 Sewer (Virtual) | Unassigned | |
Jul 14, 2021 | Cancel | 205 Plumb Soil Groundwork | Unassigned | |
none | Approved | Final Application Evaluation | Unassigned | |
Mar 26, 2021 | Approved Conditional | Water Plan Check | Unassigned | |
Mar 29, 2021 | Approved | Plan Check (Planning) | Huong Ly | tel: |
Mar 26, 2021 | Approved | Plan Check (Engineering) | Alicia Hofer | tel: |
Mar 26, 2021 | Approved | Plan Check (Building) | Don Lucas | tel: |
none | Approved | School District | Unassigned |